The project was awarded after tendering under Programme PHARE of EC. The financing of the project is from EIB.
The main types of activities under this Project executed by „Gasstroymontaj” JSC were as follows:
1. Drainage activities
2. Supporting structures
3. Building site vertical leveling
4. Construction of a pressure drainage system from HDPE pipes, φ 315, with length of 2 221 m, a pump station with 3 automatic sinking pumps with capacity of 45 l/sec.
5. Rehabilitation of a main water pipeline for Zlatni Piassatsi Resort, HDPE pipes, φ 315, total length 1 850 m.
6. Rehabilitation of Road IV-90023 – with a length of 400 m and an alley along the sea coast with a length of 1 100 m.
7. Construction of electric power cable HV and LV networks with a total length of 16 000 m, including a telephone cable network
Summary in figures
Earth works: 135 000 m3
Concrete works: 15 000 m3
Reinforcement: 1 600 t
Piles: 896 with total length 15 km and dept up to 20 m.