execution of Piles and Anchors

Project

Client

Year

Emergency earth stabilization of landslide at km 379+000 at main road E-85 (1-5) Kardzhali-Cross Border Point Makaza TRACE Kardzhali JSC 13.10.2011 21.12.2011
Landslide stabilization and reconstruction of road section of Road III-376 Prevala-Rakitovo-Kostandovo km 10+100 Eko - Hidro - 90 LTD 2010-2011
Landslide stabilization of road IV - 16061 village Rebrovo - Yablanitsa Geolobby - Kiril Angelov SP 08.12.2010 13.12.2010
Stabilization of transitions to gas pipeline branches from Bulgartransgaz transmission system in operational area of Valchi dol Bulgartransgaz EAD 2010-2011
Stabilization of Main gas pipeline-south km 47,9 and its facilities Bulgartransgaz EAD 2010-2011
Landslide stabilization in village Planinitsa, Pernik Region Pernik Municipality 07.07.2010 07.09.2010
Landslide Stabilization of East Quarter of Oriahovo Town – 2nd stage, at Danube River Bank Drilling and Casting in-situ of 328 piles, φ 800mm, 16m and 14m unit depth;
Drilling and Casting in-situ of 34 piles, φ 400mm, 10m unit depth Execution of steel concrete self-drilling anchors type ІВО R51/33 – 120pcs.х36m; 45pcs.х30m; type ІВО R38/17 – 17pcs.х12m
Bulgarian Ministry of Regional Development and Public Works 26.06.2008 30.12.2010
Stabilization of foundations of existing residential building in residential area Boiana, Sofia Execution of steel concrete self-drilling anchors type IBO R38/17 – 54pcs.x30m “Bondis” LTD 14.10.2008 26.10.2008
Stabilization of road Troian - Karnare Drilling and casting in-situ of 34 piles, φ 400mm, unit depth 8m “Pat Perfekt” JSC 06.10.2008 06.11.2008
Excavation and stabilization of the excavation for project „Office Building in Gorubliane region”, Sofia Drilling and casting in-situ of 80 piles, dia. 600mm, unit depth 12,5 m „Park” ADCIZ/ „Park Management Company” LTD 25.07.2008 15.10.2008
Results: 10 | 20 | 50


Print

tuf